TG Gallagher swiftly performed an emergency repair on a boiler plant in one of the university's dormitories. Despite the tight schedule, TGG successfully completed the repairs ahead of time.


About this Project

TG Gallagher’s Service Division has a longstanding contract with a university spanning across the Cambridge and Boston areas, providing preventative maintenance and emergency repair services. When a boiler plant failed in one of the university’s dormitories, the team responded with a swift replacement.

To align with the university’s schedule, the replacements were phased in short time increments. TG Gallagher installed new AERCO units, pumps, expansion tanks, hot water tanks, and fresh air ductwork. Additionally, the team replaced the existing copper mains.

The TGG crew worked 12 hours a day, 6 days a week, completing the project in under 3 weeks. The client was ecstatic that TG Gallagher provided a quality boiler plant a week ahead of schedule.

In Collaboration With

  • Owner University in Cambridge, MA